Technical Data

Tons/Year

50,000

Date

Start of project: 1994
Finished at: 2010

Incineration units of the Walloon Brabant Province - IBW

published on December 6, 2011

In 1994, IBH evaluated tenders for additional equipment and modification of existing incineration furnace at the Virginal plant. The project consisted of the treatment of the exhaust gas in accordance with EC regulations (100.000 Nm³/h) and the installation of new incineration stoker grate and boiler (75.000 tons/ year).
From 2001 to 2008, IBH assisted the client for the construction of an incineration train for municipal waste (50.000 tons/year) with a water cooled grate (20 MWth - Megawatts of thermal capacity), a recovery boiler and a turbo generator set (4 MWe - Megawatt electrical).

From 2005 to 2010, IBH provided its services for the provision of SCR Denox flue gas treatment of 2 incineration units (2 x 50.000 Nm3/h).