Technical Data

Services

  • Project management

Client

  • ICDI

Tons/Year

55,000

Date

Start of project: 2011
Finished at: 2017

Incineration plant of Charleroi - ICDI

published on December 6, 2011

The project (in joint venture with IGRETEC) consists of a new incineration stream of municipal and non-hazardous waste (55.000 tons/year). Civil works and refuse silo are extended. The existing incineration unit is replaced. The existing flue gas treatment equipment is reused and upgraded.

Services provided by IBH include basic engineering and architectural improvement, contractual and technical project specification, tender documentation, analysis of tender, preparation of construction contract, construction supervision and operation monitoring.