IBH s.a. (Limited)is a belgian private company of consulting engineers mainly involved in environmental projects and solid waste management.
IBH Engineering office Bourgeois et Harris s.a. | Contact
General design, contractual and technical specification, construction supervision and operation monitoring for a new incineration stream :
Technical assistance for the supervision of replacement of an existing incineration unit of 60,000 t/year : performance tests procedure, plant acceptance and follow-up of punch list of outstanding works.
Renewal of a sorting and waste to energy plant in Liège (B) in order to handle 320,000 t/year of municipal and industrial waste by mass incineration with energy recovery : 2 stoker grates of 21 t/h each with recovery boiler of 67 MWth each delivering superheated steam to a 30 MWe turbo generator ; SCR denox with ammonia injection in combustion chamber.
Preparation of tender documentation, including administrative, technical and financial specifications ; tender analysis and comparison ; contract finalisation ; construction supervision and operation monitoring.
General design, contractual and technical specifications, tender procedure, analysis of bids and contractor selection, construction supervision for the provision of SNCR Denox flue gas treatment for 2 incineration units (2 x 50.000 Nm3/h).
Feasibility Study, general design and basic engineering, contractual and technical specifications, tender procedure and analysis of bids, contractor selection, construction supervision and operation monitoring for a municipal and non-dangerous industrial incineration stream :
General design, contractual and technical specifications, tender procedure for an incineration stream of waste wood with a thermal capacity of 25 MWth with energy recovery.
Assistance to the client for the supervision of the construction of an incineration train for municipal waste (50.000 t/y) with a water cooled grate (20 MWth), a recovery boiler and a turbo generator set (4 MWe):
Feasibility study of Herstal Plant refurbishment aiming at transforming existing waste sorting / incineration units for mass burning.
Technical and Contractual assistance to the Client in relation with the modification of Herstal incineration plant : addition of flue gas treatment system (4 x 60,000 Nm3/h) for dioxins reduction.
General design, contractual and technical specifications, tendering procedure and evaluation of tenders for the extension (240,000 t/y) of the existing MSW incineration plant of Occidental Hainaut (Tournai), construction supervision and operation monitoring :
Evaluation of tenders for additional equipments and modification of existing incineration furnace at the Virginal plant (B) :
General assistance for design, tender documentation and evaluation of tenders in relation with the civil, mechanical and electrical works for the processing of the exhaust gas of the Brussels incineration plant, in accordance with the EC regulations (3 x 120.000 Nm3/h).
Technical and financial control of additional facilities to the Intradel plant including the installation of a fourth Refuse Derived Fuel (RDF) incineration stream, biogas collection and complementary leachate treatment for the existing landfill.
Basic design, tender documentation and analysis of bids relating to additional equipments for an existing sorting / composting / incineration plant (80.000 tons/year) in the Tournai area (B), including :
Construction supervision of flue gas cleaning works
Assistance to the Client, both technical and contractual, concerning the operation monitoring of the municipal waste sorting and incineration plant “Intradel”.
General design and tender documentation for the extension of the Brussels Incineration Plant in order to increase the capacity of the plant from 450,000 to 600,000 tons/year.
Technical and financial control of modification of existing Intradel Centre with addition of three Refuse Derived Fuel (RDF) incineration units with energy recovery and advanced flue gas cleaning in order to guarantee a throughput of 240,000 tons/year.
Supervision of site preparation and leachate collection for a new sanitary landfill.
Study of a municipal waste treatment plant of 150,000 t/year with energy recovery, general design, tendering procedure and selection of contractor.
The project includes both construction and operation commitments with selected contractor.
Study of the installation of a third incineration stream to increase the plant throughput to 225,000 t/y.
General design of an incineration plant with a capacity of 460,000 tons per year with energy recovery, selection of tender candidates and preparation of the tender documents.
Evaluation of bids, preparation of contract documents.
Technical and financial control during the construction of the plant, assistance to the client for the acceptance procedure and performance tests.
Monitoring of the operation and maintenance of the plant.
Technical and contractual assistance to the Client for a Waste Management Centre (CCRG) comprising a Plant of MSW pre-treatment PBM (biological drying of 200,000 t/y) and a Waste to Energy Plant PVE for 240,000 t/y of MSW :
Technical and contractual assistance to the Client for a 100 MW Power Plant including a combined cycle (Gas Turbine) and a MSW incineration stream (240,000 tons of municipal waste per annum) :
The project includes 1 Waste to Energy Plant, 1 Material Recycling Facility, 2 Landfill Sites and 2 Transfer Stations in order to dispose of 240,000 t/y municipal waste.
The services provided by IBH include :
Project management and technical assistance services aiming at the fulfilment of HWS‘ contractual obligations for the construction of a WTE Plant (200,000 t/y) as required by the Staffordshire Council.
Project management and technical assistance services aiming at the fulfilment of WWS‘ contractual obligations for the construction of a WTE Plant (105,000 t/y) as required by the Council of the Borough of Wolverhampton.
Project management and technical assistance services aiming at the fulfilment of DWS‘ contractual obligations for the construction of a WTE Plant (90,000 t/y) as required by the Council of the Borough of Dudley.
Technical assistance during Manufacturers Defect Period : advice on technical matters, comments on compliance with operation agreement and authorizations, report on the plant operation and maintenance (400,000 t/y WTE Selchp Plant in East London).
Technical advice and examination of bids for an incineration plant (135,000 tons/year) with stoker grate or fluidized bed for the urban district of Mantes (F).
Review of technical documentation for an incineration and composting plant, construction programme and project cost.
Preparation of regular reports on project progress and factors which might affect the construction loan.
General analysis of tenders regarding a municipal waste treatment project (100,000 t/y) for the district association SIDRU.
Technical assistance including specific responsibility for the process refuse streams from waste handling to chimney emissions ; contractual advice , project management and cost control assistance during the construction phase of an Waste to Energy plant of 400,000 tons/year in East London.
Control of feasibility study of a 200,000, t/year incineration plant.
Technical assistance for the plant general design, preparation of tender documents for separate contracts : furnaces, boilers, exhaust gas treatment, electricity generation...
Consultancy service to the Consortium Members on the construction and the operation of a 400,000 t/y incineration plant with electricity production to be installed in East London ; advice on contractual and technical matters.
IBH s.a. copyright © 1999-2009 All rights reserved. Powered by Nikita Concept